Projects to be solicited through June 2023
Under $25 million
Project |
Method |
Agency |
---|---|---|
HVAC, Fire Control, & CNG Upgrades: Spring Creek & College Point Bus Depots |
DBB |
MTAB |
Installation of Fire Suppression System: Hugh L. Carey Tunnel & Queens-Midtown Tunnel |
Design Build |
B&T |
Lighting: Fresh Pond Yard |
DBB |
NYCT |
Sandy Resiliency 4 Pump Rooms: Jerome/Pelham Tube |
DBB |
NYCT |
Stormwater Mitigation (Street Stairs Package 1): 4 locations in Manhattan |
DBB |
NYCT |
Fall Protection Improvements: West Side Shop |
DBB |
LIRR |
APC Power Plant Replacement & HVAC: Communications Rooms System-wide |
DBB |
NYCT |
Boiler Replacement: LaGuardia & Spring Creek Bus Depots |
DBB |
MTAB |
Boring Services: Brooklyn, Queens, & Staten Island |
DBB |
NYCT |
Boring Services: Manhattan & the Bronx |
DBB |
NYCT |
Chassis Wash: Grand Av & Flatbush Depots |
DBB |
NYCT |
Construct Pump Room: Rockwell Place / 4 Av |
DBB |
NYCT |
Elevator Replacement: Kingsbridge & Michael J. Quill Bus Depots |
TBD |
NYCT |
Security Cameras & Expansion: Grand Central Terminal |
DBB |
MNR |
Generator Replacement: Spring Creek & College Point Bus Depots |
DBB |
MTAB |
HVAC: East New York & Queens Village Depots |
DBB |
NYCT |
Rehabilitation: Atlantic Terminal |
DBB |
LIRR |
Rehabilitation of Emergency Exits: 14 Locations System-wide |
Design Build |
NYCT |
Replace High Tension Switchgear at 4 Substations and DC Lineup: 86 Av Substation / Queens Blvd Line |
DBB |
NYCT |
Resiliency Improvements: Rail Control Center |
Design Build |
NYCT |
Overpass Painting: Ronkonkoma Parking Garage |
DBB |
LIRR |
Station Access / Parking Improvements: Various Locations on the Far Rockaway / Port Washington / Ronkonkoma Lines |
DBB |
LIRR |
Stormwater Mitigation (Street Stairs Package 2): 14 Stations in Manhattan, the Bronx, Queens, and Brooklyn |
DBB |
NYCT |
Upper Level North Abutment & Retaining Wall Reconstruction & Bike / Pedestrian Access Ramp: Henry Hudson Bridge |
DBB |
B&T |
Water Remediation: Atlantic Av-Barclays Center |
Design Build |
NYCT |
Widening: Southbound FDR Drive, 125 St Entrance Ramp to 116 St Exit Ramp |
DBB |
B&T |
HVAC Replacement: Richmond Hill (McGurl Facility & Locomotive Shop) |
TBD |
LIRR |
Freight Elevators: Hillside Support Facility |
TBD |
LIRR |
Yard Fencing: Fresh Pond Yard |
DBB |
NYCT |
Between $25 million and $100 million
Project |
Method |
Agency |
---|---|---|
Early Works / Utility Relocation: Second Avenue Subway Phase 2 |
DBB |
NYCT |
Mainline Switch Rehabilitation: Staten Island Railway |
DBB |
NYCT |
Replace Equipment: 9 Substations on the 8 Av, Dyre, Concourse, & Queens Blvd Lines, & Jamaica Yard |
DBB |
NYCT |
Structure Painting: Myrtle Line Outstanding Work |
DBB |
NYCT |
Substation Renewals: 3 Locations on the 6 Av, Culver, & Queens Blvd Lines |
DBB |
NYCT |
Station Renewal: Botanical Gardens, Woodlawn, and Williams Bridge / Harlem Line |
Design Build |
MNR |
Rehabilitation: Garretson Av Bridge & Stapleton Viaduct / Overcoating: 6 SIR Bridges (Thompson St, Wave St, Water St, Bay St, Prospect St, Canal St) / Component Repairs: 7 SIR Stations (St. George, Stapleton, Grasmere, Old Town, Dongan Hills, Grant City, Oakwood Heights) |
DBB |
NYCT |
Connection-Oriented Ethernet (COE) Phase 3C: System-wide |
DBB |
NYCT |
Emergency Alarms Phase 1: Various Locations System-wide |
Design Build |
NYCT |
Fire Stand Pipe Phase 2: Grand Central Terminal |
Design Build |
MNR |
Passenger ID CCTV: Additional Locations System-wide |
Design Build |
NYCT |
Police District Office Rehabilitation: 14 St-Union Square |
Design Build |
NYCT |
Police Facility Area Rehabilitation: Port Authority Bus Terminal |
Design Build |
NYCT |
Replace 17 Elevators: 8 Stations (Pacific St, Atlantic Av - IRT, Atlantic Av - BMT, Church Av, Utica Av, DeKalb Av, Prospect Park, Stillwell Av) |
Design Build |
NYCT |
Replace 20 Elevators: 9 Stations (Fordham Rd, 14 St / 8 Av, 66 St / 7 Av, 72 St / 7 Av, Canal St / Lexington Av, Main St, Roosevelt Av, Queens Plaza, 179 St) |
Design Build |
NYCT |
Station Renewals: Chambers St / Nassau & 190 St / 8 Av |
Design Build |
NYCT |
Upgrade Cable Shop Phase 1: Atlantic Av |
Design Build |
NYCT |
Overhaul & Replace Facility Monitoring & Safety Systems: Various Locations System-wide |
Design Build |
B&T |
Upgrade Asynchronous Fiber Optic Network to SONET - Ring E |
DBB |
NYCT |
Over $100 million
Project |
Method |
Agency |
---|---|---|
ADA: Broadway Junction Complex |
Design Build |
NYCT |
ADA LIRR Package 2: Stations To Be Identified on the Main, Montauk, Port Washington and/or Port Jefferson Lines |
Design Build |
LIRR |
ADA NYCT Package 5: 13 Stations on Various Lines |
Design Build |
NYCT |
ADA: 168 St / 7 Av-Broadway |
Design Build |
NYCT |
Anchorage & Tower Protection, Bridge Structural Lighting & Misc Structural Upgrades, Main Cable and Suspender Rope Investigation, Facility-Wide Painting: Throgs Neck Bridge |
Design Build |
B&T |
Platform Replacement: Babylon Station |
Design Build |
LIRR |
Southeast Parking Improvements: Brewster Yard |
Design Build |
MNR |
Line Structure Component Repairs, Stormwater Mitigation, & Repair Expansion Joints: Broadway-7Av / 8 Av N ROW |
DBB |
NYCT |
Sandy Repairs (Power Repairs and Rehabilitation of Circuit Breaker Houses): Various Locations |
Design Build |
NYCT |
Replace 21 Escalators: Systemwide |
Design Build |
NYCT |
Sandy Repairs: Culver Yard |
DBB |
NYCT |
West End Overcoating: 9 Av Portal - Stillwell & Structural Repairs: 9 Av |
DBB |
NYCT |
Tower Lighting and Electrical Upgrades Phase 2 & Facility-wide Painting: Verrazzano Narrows Bridge |
Design Build |
B&T |
Switch Replacements & Interlockings: 6 Av CBTC |
Design Build |
NYCT |
Projects to be solicited through December 2023
Under $25 million
Project |
Method |
Agency |
---|---|---|
Car Washer Component Repairs: Canarsie, Jamaica, & 207 St |
DBB |
NYCT |
Subway Facility Heating & Energy Efficiency Boiler Upgrades: Concourse Yard, Coney Island Yard, 240 St Maintenance Facility, Jerome Maintenance Facility, Tiffany Shop, E 180 St Yard, and East New York Maintenance Facility |
TBD |
NYCT |
Drainage & Fire Protection: Charleston Bus Depot |
DBB |
NYCT |
Relocate: East Yaphank Station |
TBD |
LIRR |
Discharge Line Rehabilitation: Greenpoint Tube |
DBB |
NYCT |
Sandy Mitigation Flood Protection: World Trade Center Site |
TBD |
NYCT |
Stormwater Mitigation (Miscellaneous Vulnerabilities): Various Locations |
DBB |
NYCT |
Stormwater Mitigation (Vents): Various Locations |
TBD |
NYCT |
Upgrade / Replace Private Branch Exchange (PBX): Jay St |
DBB |
NYCT |
Upgrade / Replace Elevators: Various Department of Subways Facilities |
DBB |
NYCT |
Water Conditions Remedy: Various Locations |
DBB |
NYCT |
Between $25 million and $100 million
Project |
Method |
Agency |
---|---|---|
Component Repairs: Various Fan Plants |
DBB |
NYCT |
Boilers, HVAC, and Air Curtain Replacement: Castleton, Michael J. Quill, Gun Hill, Jackie Gleason, Ulmer Park, and Kings Bridge Depots |
DBB |
NYCT |
Resiliency Improvements: Westchester & Corona Yards |
DBB |
NYCT |
Roof Repairs: Coney Island Overhaul Shop, 215 St Signal Shop, & Various Substations |
DBB |
NYCT |
Sandy Mitigation (Existing Pump Room Enhancements and Rehabilitate Pump Rooms): 13 Locations in Manhattan, Brooklyn, and the Bronx |
DBB |
NYCT |
Sandy Mitigation (Outstanding Street Level Openings): Various Locations |
DBB |
NYCT |
Substation Renewal: Washington Heights and Village |
DBB |
NYCT |
Over $100 million
Project |
Method |
Agency |
---|---|---|
Overcoating: 225 St - 240 St / Broadway-7 Av, Queensboro Plaza - 33 St / Flushing and Portal to Kings Hwy / Culver |
DBB |
NYCT |
Public Address / Customer Information Signs (PA/CIS) Upgrade Phase 0: B-Division System-wide |
Design Build |
NYCT |
Component Repairs: 43 Stations Various Lines |
ProgressiveDesign Build |
NYCT |
Second Avenue Subway: Tunnel Boring Machine and Caverns |
Design Build |
NYCT |
Platform / Mezzanine Component Repairs: 39 Stations System-wide |
Design Build |
NYCT |