What we’re doing
From June 28 to September 3, service on the
line was partially suspended in three phases:- From June 28 to July 5, trains didn’t run between Court Sq and Nassau Av.
- From July 5 to August 11, trains didn’t run between Court Sq and Bedford-Nostrand Avs.
- From August 12 to September 3, trains didn’t run between Bedford-Nostrand Avs and Church Av.
Why we’re doing it
The Crosstown Line, used by the
train, still has its original signal system from when it opened over 90 years ago. This system is now past the end of its useful life. So, we’re bringing the latest in communications-based train control (CBTC) technology to the Crosstown Line. A more modern, reliable signal system means more reliable service for the 160,000 riders who take the each day.We partially suspended service 24/7 in three phases because this will allow us to complete the work much more quickly than working only overnight or on weekends. This will help us reach our goal of fully upgrading the signal system on the Crosstown Line by 2027.
Service changes
Phase 1: June 28-July 5
- During Phase 1, from 9:45 p.m. Friday, June 28 to 9:45 p.m. Friday, July 5, trains didn’t run between Court Sq and Nassau Av in either direction.
Phase 2: July 5-August 11
- During Phase 2, from 9:45 p.m. Friday, July 5 to 8:30 p.m. Sunday, August 11,
- From 8:30 p.m. Sunday, August 11 to 4 a.m. Monday, August 12, trains didn’t run at all while we transitioned from Phase 2 to Phase 3 of service changes.
trains didn’t run between Court Sq and Bedford-Nostrand Avs.
Phase 3: August 12-September 3
- During Phase 3, from 4 a.m. Monday, August 12 to 5 a.m. Tuesday, September 3, trains didn’t run between Bedford-Nostrand Avs and Church Av.